Laboratory Glassware Washer Validation Benefits

To appreciate how labwasher cleaning validation can help your organization, it helps to take a bird’s eye view of its objectives. They are to ensure consistency, quality and compliance with the FDA’s Current Good Manufacturing Practice (cGMP) regulations — regulations with a laser focus on a manufacturing process’ ability to create safe and effective products. Again and again.
The validation procedure starts with examining the big picture, the cleaning process, and then investigates the equipment that plays a pivotal role in executing each task. The purpose of the exercise is to furnish evidence to assure regulators and customers. This data you gather shows in black and white that your cleaning process will consistently deliver laboratory glassware that meets required specifications for cleanliness.
Many benefits flow from these objectives. They include:
1. Conformance with Regulatory Requirements
Validating all of the processes involved in bringing a drug to market is not an option. It is an FDA requirement. The most obvious reason for validation, therefore, is to ensure that your lab glassware cleaning process is in compliance with the FDA’s regulations.
2. Reduced Downtime
Since labwasher validation guarantees residue-free washing results every time, it enables you to avoid downtime due to dirty glassware.
3. Improved Quality
In pharmaceuticals, quality cannot be an afterthought. Because validation focuses the two essential ingredients of pharmaceutical quality, safety and efficacy, it is a natural step toward a goal of quality improvement. It make sure that medicinal products will perform according to expectations and the risk of contamination from impurities is brought as close to zero as possible.
4. Reduced Risk of Recalls
Contamination of drugs due to poor cleaning processes can compromise their safety and effectiveness, resulting in health hazards and even fatalities. Product recalls follow quickly on the heels of tainted drugs, shaving bottom lines, eating up time and sullying reputations. Clearly, all manufacturers strive to avoid such disasters.
5. Productivity
The validation process makes sure you have a systematic approach that produces good results without fail. In this way, it improves productivity. Because of the efficiency-boosting power of validation, even labs involved strictly with preliminary research and discovery that work outside of cGMP environments, are validating their cleaning processes. These labs include, for example:
  • Non-pharmaceutical labs that create products for clinical testing under cGMP
  • Contract labs that must use ironclad to avoid cross-contamination between multiple customers’ orders
  • Quality control labs
  • Labs involved in preliminary research and discovery
Obviously, there are many benefits to labwasher validation that go beyond compliance with cGMP regulations. These include increasing quality, productivity, and speed to market as well as reducing downtime and recalls. Given the many advantages of labwasher validation, you may be ready to get started with the process. How you do so will depend on the precise nature of your operations. However, there are usually three steps. First, define the cleaning process. Next, describe it in detail, usually including written standard operating procedures. Finally, qualify the labwasher and validate the cleaning process.

Validation Strategies For Nonsterile Solid Dosage Forms

Process qualification, which includes pharmaceutical drug products at a stage prior to commercialization or prior to submitting a New Drug Application (NDA) or Abbreviated New Drug Application (ANDA).  In this stage, it must be demonstrated that the process for manufacture of a drug product is consistent and can produce drug products that are compliant with the Food and Drug Administration’s requirements for filing. 

This stage includes two elements.  The first element focuses on facility design and equipment installation and maintenance while the second includes process performance qualification (PPQ).  Some prerequisites to facility design and equipment installation and maintenance includes validation and qualification of analytical methods, approved standard operating procedures (SOPs) for process validation, implementation of preventive maintenance program (PMs), cleaning validation of equipment, and process specific GMP training.  In structuring a PPQ, CPPs and CQAs must be defined, justified, and documented.  Other process performance qualification activities must be controlled by an approved protocol that includes the scope, strategy, testing, sampling plan, and acceptance criteria. This study is conducted at a manufacturing site, according to a site validation master plan.  Additional strategies are explored below.

Process Qualification Study Strategies:

A strategy needs to be developed for every qualification study and it must be based on deep process understanding gained from the manufacturing experience. Some elements to consider include:

1. Number of Batches: The protocol should include three consecutive batches, with the results summarized in the final process qualification report.

2. Material Selection:  Selection of more than one lot of API and critical raw materials should be used during process qualification (especially if the API or critical raw materials are not dissolved or distributed in solution). Based on the selection of these materials, a process should be designed to validate the robustness of the process.

3. Equipment Selection: The process must be qualified on all equipment intended to be used in the manufacture of the product. For equipment determined as being equivalent, qualification on one piece of equipment is sufficient.

4. Design Space/Parameters Ranges:  For products that have an established design space, the process qualification should be executed at specified conditions within the design space. For conditions that are high risk, high and low parameter ranges should be considered for the process qualification.

5. Process Re-qualification:  Process re-qualification may be required if, for example, a significant deviation from desired process performance is uncovered through stage 3 continued process verification.  The process re-qualification studies should bridge back to the original or pivotal clinical biobatch.

Process Qualification Testing:

Process qualification testing should be based on the established CPPs and CQAs and the control strategy and risk assessments, which characterize the product quality and process consistency.

CPP Monitoring:  Defined critical process parameters should be monitored and reported in the final qualification report.

  • For processes that have a processing fluid (e.g., granulation), microbial testing and hold times will need to be established. For processes where critical ingredients are added as a part of the processing fluid, testing related to the critical ingredient (e.g., assay) at make-up and at the end of hold time should be considered.  
  • For processes involving lubricated granulation, blend uniformity testing must verify that the active ingredient has been distributed throughout the blended bulk uniformly. To determine unit-dose equivalent (1-3x) blend uniformity of the active ingredient on the final, blend samples should taken from the blender. For combination products, all APIs need to be tested for blend uniformity while respective blenders need to be tested for bilayer tablets.
  • For the manufacture of compressed tablets or capsules, during the compression operation a sampling plan should be adopted with around ten evenly spaced intervals throughout the batch processing. After the compression machine is set-up, location one should include the first salable dosage units and location ten should contain the last salable dosage units while location two through nine should be evenly spaced across the lot.  For a process using a double sided machine, both the sides of the machine should be sampled at each location. For the manufacture of combination or bilayer tablets, ample samples should be obtained to properly evaluate all API specific tests.  Specific to bilayer tablets, samples should be taken to evaluate both layers.
  • For the manufacture of film coated tablets, random location sampling should be taken of representative samples. For application of functional membranes, testing should be performed on samples taken from each film coating pan load. For nonfunctional coats, samples may be divided among the film coating pan load.

Acceptance Criteria:

The manufacture process must be validated and reported within the regulatory filing, batch records and final validation report, including all the appropriate specification and procedures (e.g., selected CPPs and release requirements). Any deviation must be investigated and addressed in the validation report. 

Each of the processing steps can be analyzed by evaluating the process control charts (based on three sigma limits) and the historical process capability charts.  These charts should be evaluated for nonrandom systematic behavior.  Ultimately, for all initial process qualification, a comparison must be made to the dissolution profile performed on the biobatch or pivotal reference batch.  A batch may be excluded if a nonprocess related assignable cause, like mechanical failure, has been identified.

Statistical Analysis:

Intra-batch and inter-batch variability should be examined from data collected during process qualification through the analysis of process control charts and process capability charts.

Once a product has completed performance qualification, process validation continues through implementation of continued process verification.  This verification includes monitoring operating procedures, preventive maintenance and calibration programs, deviation investigations, annual review, and change control procedures. Any changes to the process must be evaluated through the process change request system and procedures for process change control to determine the impact to on-going process validation.  A list of intermediate tests for nonsterile solid dosage forms (tablets and capsules) are compiled in Table 1.

Stage 2 process qualification is conducted at the manufacturing site, which is usually a far distance away from product development/process development facilities. Therefore, another important piece of the process validation includes technology transfer to manufacturing facilities. Technology transfer includes detailed process fit, manufacturing readiness, and an execution phase. Process qualification falls under the execution phase.

Continued Process Verification (Stage 3)

The goal of continued process verification (CPV) is “continual assurance that the process remains in a state of control (validated state) during commercial manufacture.”[5] Once a process has gone through process qualification, an ongoing program to collect and analyze product and process data that relate to product quality is necessary. The objective of the on-going process verification program is to understand the sources of variation, its impact on the process and product attributes, and finally to devise a way to control the variation. The knowledge gained through stage 3 of continued process verification provides ongoing assurance that a product remains in a state of control.

In summary, QbD is not a mandated requirement, however, any pharmaceutical company that instills the QbD approach in their DNA of product development (process design, process qualification, and continued process verification) will come out ahead in their value curve, since we live in an increasingly science-driven regulatory environment in 21st century — where compliance and quality have been essential elements of competitiveness and quality drug products. Hopefully these tips and strategies will support you in designing and validating a quality manufacturing process.




AHU Validation : The Concept

The degree of cleanliness of air in the pharmaceutical manufacturing and related operations area should be established depending on the characteristics of products and operations in the area.

In order to establish and maintain such standards, careful attention has to be exercised to keep the standards from the stage of design and construction through to the monitoring in the stage of routine operations.

Air Quality

A total air handling system, covering the open air intake, treatment, the supply to the manufacturing area, and the exhaust, should be designed and validated. The handling system contains units or prefiltration, temperature and humidity control, final air filtration, return and exhaust. When the air is supplied to the manufacturing area, care is required in maintaining the required air quality during the operation or at the point of product exposure to the environment.

This point is closely related to the layout and construction features of the manufacturing area.

  • The air flow from the critical or most clean area to the surrounding area; that is, the less clean area. For this purpose, rooms used for the manufacturing operation have to be laid out according to the order of the required air cleanliness.

  • In order to maintain the air cleanliness in the area and airflow, the amount of air supplied and exhaust have to be balanced to keep the designed air exchange ratio, airflow pattern, and air pressure differentials. In each room the operation site should be maintained in the most suitable status.


For each purpose, the following items must be carefully controlled.
  • Locations and number of air supplies
  • Locations and number of air exhausts
  • Ratio of air exchange
  • Return ratio of exhaust air
  • Location of local air exhaust, if necessary
  • Airflow pattern at the site of product exposure
  • Air velocity at the point of product exposure


These features have to be well designed, installed, validated, and maintained. Critical operation has to be performed under the unidirectional airflow (laminar airflow). Air turbulence deteriorates air quality by intake of air from surrounding less clean areas.

The amount of air supplied and exhausted is related to the air pressure differentials. After the system is validated, air quality should be continuously monitored and maintained during manufacturing operations.
Filters used for the prefiltration and final filtration should be maintained to operate to their design specifications. Deterioration of filters is caused by leakage and/or accumulation of particles. The former is tested by periodical integrity test (usually dioctylphthalate DOP test), and the latter is tested by the increase of air pressure differentials between the upstream and downstream sides of the filter.

Regulations and Standards

All of the environmentally-controlled areas of pharmaceutical manufacturing and its related areas should meet the requirement of air cleanliness, which is expressed as classification specified by official standards, such as ISO (International Organisation of Standardisation) or FED-STD (U.S federal standard) 209, and/or GMP.

Autoclave Validation / Qualification : 10 Steps

Autoclave Validation / Qualification is mandatory for all machines used for biological sterilization, in the biomedical and pharmaceutical industries. Sterilization can be accomplished by either physical or chemical means. The principal physical means is autoclaving; other physical methods include boiling and dry heat.
Chemicals used for sterilization include the gases ethylene oxide and formaldehyde, and liquids such asglutaraldehyde . Of all these sterilants, autoclaving is the fastest and most reliable, which is why the regulators always scrutinize autoclave validation / Qualification activities.

Here are 10 items to consider when qualifying autoclaves.

1. Testing of Steam for Porous Product Sterilization

Before commencing temperature testing the correct conditions must be satisfied. The first condition for sterilization of porous product is saturated steam quality. The ideal for steam sterilization is dry saturated steam and entrained water (dryness fraction รข‰¥ 97%). The largest heat transfer occurs when the steam is at boundary conditions. If the steam is dry or contains gas then it cannot condense and its effectiveness is reduced.

2. Equipment Used for Testing

The equipment used must support 21 CFR Part 11 and must be of adequate accuracy. Testing with equipment that is not appropriate can be a major problem so also buy from a trusted vendor. As a small temperature range is required for accuracy (A few degrees) the accuracy of the equipment is very important for the overall measuring chain.

3. System Description of Autoclave

The first impression is very important when the qualification of critical equipment such as an autoclave is at stake. A good description of the system in a protocol shows that you understand how the process works and which critical points you need to keep under control. This description must contain the programs that are used, how they work, how many, where the control probes are located and what regulates this process.

4. Operating Instructions, Calibration and Maintenance

Before the temperature is tested it must be checked whether the operating instruction are valid, whether the instruments are calibrated and what was changed in the system since the last qualification occurred.
Operating Instructions must include parameters of sterilization, the scheme item and position of the control probes in the chamber. The emphasis is on the calibration of instruments because small errors in temperature can affect the Fo value to a great extent.

5. Procedure

One of the most common mistakes is inaccurate testing procedures. The test procedure must be unambiguous and accurate and must not leave the possibility for different interpretations.
Ambiguous: Put the thermocouple in a glass bottle.

Unambiguous: Put the thermocouple in a glass bottle at the contact between the bottom of the bottle and the side of the bottle (This is the most critical place to collect condensate).

6. Load

The most common objections are about loads. That they are not sufficiently described and that regular production does not reflect the qualified load being used.

This can be avoided by item photographing and releasing the same patterns in the protocol and work instructions. This will avoid the arbitrary interpretation of descriptive configuration.

Although sometimes this may seem trite the differences in the temperature profiles of the solution and air filters can be great. Pay special attention to the worst case loads and explain the rationale (mostly filter and silicone hose).

7. The Position of the Thermocouples

The position of the thermocouples must be unambiguous and precise to avoid different interpretations by individuals that perform tests or inspections. You do not want to enter into a debate about where the thermocouple is positioned.

Of course, the critical areas must be covered, and this must be explained in the rationale. When sterilizing liquid loads studies must be done to define coldest and warmest point for min and max load.

8. Acceptance Criteria in the Heat Penetration Tests

Since there are differences in the standards (e.g. PDA Technical Report and EN 285) it would be best if all eligibility criteria are taken into account. Special emphasis should be on equilibration time and temperature because it is a requirement for a good Fo.

9. Deviations

Deviations cannot be forgotten as they may be encountered regularly throughout the qualification process. A robust deviation management process should exist as they may impact the quality of the product. Good handling of deviations help us to improve our qualification, though they are often viewed negatively and not as a mechanism for process improvement.

10. Reports

The report should be accurate as it eliminates the use of data from the protocol and the ability to find errors in them. The report should contain the time and the date of tests, parameters, results related to temperature, BI results , positions of themocouples, Fo and comparison of results from initial and previous qualification in order to see in which direction the process is moving.